Legislation Details

File #: 24-472    Version: 1
Type: Consent Calendar Items Status: Agenda Ready
In control: City Council
On agenda: 2/28/2024 Final action:
Title: Notice of Completion for the Work performed by California Professional Engineering, Inc. for the Traffic Signal and Median Improvements on Brookhurst Street - Project No. P-2536.
Attachments: 1. Attachment 1 - Notice of Completion -Bolsa Signal-CPE

Westminster City Council

 

SUBJECT

 

Title

Notice of Completion for the Work performed by California Professional Engineering, Inc. for the Traffic Signal and Median Improvements on Brookhurst Street - Project No. P-2536.

End

End

End

publichearing

End

From:                                          Jake Ngo, Public Works Director/City Engineer

Requested by:                     Administration

Prepared by:                     Tuan Pham, Assistant City Engineer

____________________________________________________________

 

RECOMMENDED ACTION

 

Recommendation

Authorize an additional amount of $4,334 from Account No. 20002-001900 for additional change orders related to the project and accept the subject project and authorize the City Clerk to file a Notice of Completion with the County Recorder’s Office.

 

end

BACKGROUND

 

The subject project was awarded by the Mayor and City Council on October 13, 2021. The contract has been satisfactorily completed by California Professional Engineering, Inc. The approved bid amount with 10% contingency was $457,370.10, and the final contract amount was $461,703.15. The additional amount was due to unforeseen field conditions which required the removal of excess groundwater, addressing Southern California Edison’s additional requirements, and furnishing a controller.

 

The work consisted of removing and replacing existing concrete median, curb, gutter, and pavement; placing aggregate base and asphalt concrete overlay; installing handicap ramps, traffic signal system, traffic signal poles, fiber optic, conduits, controller, cabinet, video detection system, striping, and pavement markings.

 

 

 

 

FISCAL IMPACT

 

The total construction cost, in the amount of $461,703.15, for the contract with California Professional Engineering, Inc., is budgeted in the CIP Account No. 20002-001900 “Bolsa Avenue and Brookhurst Street Corridor Traffic Improvement.”

 

LEGAL REVIEW

 

The City Attorney’s Office has reviewed as to form.

 

CONCLUSION

 

The contract has been satisfactorily completed by California Professional Engineering, Inc. The next step is to accept the subject project and authorize the City Clerk to file a Notice of Completion with the County Clerk-Recorder’s Office.

 

ATTACHMENTS

 

1.                     Notice of Completion

 

REVIEWED BY

 

Erin Backs, Finance Director

Christian Bettenhausen, City Attorney

Christine Cordon, City Manager