Legislation Details

File #: 24-542    Version: 1
Type: Consent Calendar Items Status: Agenda Ready
In control: City Council
On agenda: 4/24/2024 Final action:
Title: Notice of Completion for the Work Performed by All Cities Engineering, Inc. for the Newland Street Waterline Improvements Project, Project P-2574.
Attachments: 1. Attachment 1 - Notice of Completion -Newland Waterline Project

Westminster City Council

 

SUBJECT

 

Title

Notice of Completion for the Work Performed by All Cities Engineering, Inc. for the Newland Street Waterline Improvements Project, Project P-2574.

 

End

End

publichearing

End

From:                                          Jake Ngo, Public Works Director/City Engineer

Requested by:                     Administration

Prepared by:                     Tuan Pham, Assistant City Engineer

____________________________________________________________

 

RECOMMENDED ACTION

 

Recommendation

Accept the subject project and authorize the City Clerk to file a Notice of Completion with the County Clerk-Recorder’s Office. 

 

end

BACKGROUND

 

The subject project, with the original bid amount of $580,950.00, was awarded by the Mayor and City Council on September 13, 2023. The contract has been satisfactorily completed by All Cities Engineering, Inc. The final contract amount of $610,929.06, which included contract change orders to address a couple of existing pavement depressions. 

 

The scope of work involved the installation of new fire hydrants, water mains, curb, gutter, sidewalk, handicap ramp, trench paving, applying slurry type II, and installing striping and pavement markings.

 

FISCAL IMPACT

 

The total construction cost in the amount of $610,929.06, for the contract with All Cities Engineering, Inc., is budgeted in the CIP Account Number 55502-552400 “Citywide Waterline Improvements.”

 

LEGAL REVIEW

 

The City Attorney’s Office has reviewed as to form.

 

CONCLUSION

 

The contract has been satisfactorily completed by All Cities Engineering, Inc. The next step is for the City Council to approve the subject project and authorize the City Clerk to file a Notice of Completion with the County Clerk-Recorder’s Office.

 