Legislation Details

File #: 26-1315    Version: 1
Type: Consent Calendar Items Status: Agenda Ready
In control: City Council
On agenda: 3/25/2026 Final action:
Title: Notice of Completion of the Work Performed by Western State Builders, Inc. for the Playground Renovation Project for Elden F. Gillespie Park - Project Plan No: P-2639.
Attachments: 1. Attachment 1 - Notice of Completion - Gillespie Park, 2. Attachment 2 - Project Progress Photos

Westminster City Council

 

SUBJECT

 

Title

Notice of Completion of the Work Performed by Western State Builders, Inc. for the Playground Renovation Project for Elden F. Gillespie Park - Project Plan No: P-2639.

End

 

From:                                          Jake Ngo, Public Works Director

Requested by:                     Administration

Prepared by:                     Cindy Huynh, Civil Engineering Associate

____________________________________________________________

 

RECOMMENDED ACTION

 

Recommendation

Accept the subject project and authorize the City Clerk to file a Notice of Completion with the County Clerk-Recorder’s Office.

 

end

BACKGROUND

 

On April 9, 2025, the Mayor and City Council approved the plans and specifications for the subject project and authorized staff to advertise the project. On June 11, 2025, the contract was awarded to Western State Builders, Inc. in the amount of $352,143.45, with a 10% contingency allowance of $35,214.35 for potential change orders, bringing the total approved project amount to $387,357.80. This project is funded by CDBG and Park Dedication funds.

 

The original scope of work consisted of:

 

•                     Removing and disposing of the existing concrete flatwork, playground equipment, footing, sand, and rubber playground surface;

•                     Performing site grading for the new playground; and

•                     Installing new playground equipment, footing, rubber playground surface, concrete sidewalk, curb, landscaping, and benches.

 

The contract has since been completed by Western State Builders, Inc. A total of $34,194.08 in change orders was approved, bringing the final project cost to $386,337.53. The additional funding used is within the previously approved contingency amount. The increase is due to extra quantities of concrete sidewalk and landscaping work. The following table summarizes the approved change orders/deductive change orders:

 

Change Order

Purpose

Amount

CCO 01

Remove and replace additional 4-inch thick sidewalk (near the playground area).

$27,842.92

CCO 02

Deduct rebar installation from the scope of work for bid item 5 (install 4-inch thick sidewalk). 

   ($1,037.00)

CCO 03

Additional landscaping work for grading and sod installation.

$7,388.16

TOTAL

 

$34,194.08

 

The work performed by Western State Builders Inc. has been inspected and approved by the landscape architect, a third-party licensed playground inspector, and city staff.

 

The ribbon-cutting date for the new playground is scheduled for April 1, 2026, at 2:00 PM.

 

FISCAL IMPACT

 

The total construction cost, in the amount of $386,337.53, for the contract with Western State Builders, Inc., is budgeted in the following accounts:

 

•                     Account No. 16510-162401, “Playground Replacement Elden Gillespie” in the amount of $314,313.

•                     Account No. 76502-762504, “Playground Replacement Elden Gillespie” in the amount of $72,024.53.

 

LEGAL REVIEW

 

The City Attorney’s Office has reviewed as to form.

 

 

 

CONCLUSION

 

The contract has been satisfactorily completed by Western State Builders, Inc. It is recommended that the Mayor and the City Council accept the subject project and authorize the City Clerk to file a Notice of Completion with the County Clerk-Recorder’s Office.

 

ATTACHMENTS

 

1.                     Notice of Completion

2.                     Project Progress Photos

 

REVIEWED BY

 

Erin Backs, Finance Director

City Attorney’s Office

Christine Cordon, City Manager