Legislation Details

File #: 26-1316    Version: 1
Type: Consent Calendar Items Status: Agenda Ready
In control: City Council
On agenda: 3/25/2026 Final action:
Title: Notice of Completion of the Work Performed by Zeco, Inc. for the Sigler Park Soccer Fields Project - Project Plan No: P-2618.
Attachments: 1. Attachment 1 - Notice of Completion - Zeco-Soccer, 2. Attachment 2 - Project Progress Photos

Westminster City Council

 

SUBJECT

 

Title

Notice of Completion of the Work Performed by Zeco, Inc. for the Sigler Park Soccer Fields Project - Project Plan No: P-2618.

End

 

From:                                          Jake Ngo, Public Works Director

Requested by:                     Administration

Prepared by:                     Tuan Pham, Maintenance and Utilities Manager

____________________________________________________________

 

RECOMMENDED ACTION

 

Recommendation

Accept the subject project and authorize the City Clerk to file a Notice of Completion with the County Clerk-Recorder’s Office.

 

end

BACKGROUND

 

On September 11, 2024, the Mayor and City Council approved the plans and specifications for the subject project and authorized staff to advertise the project. On November 13, 2024, the contract was awarded to Zeco, Inc. in the amount of $2,144,579.00, with a 10% contingency allowance of $214,457.90 for potential change orders, bringing the total approved project amount to $2,359,036.90. This project is funded by ARPA, Park Dedication and Municipal Lighting funds.

 

The scope of work consisted of:

 

•                     Demolition of existing baseball infield;

•                     Removal of equipment, bleachers, sport lighting system, trees, and irrigation system;

•                     Grading for new soccer fields, installation of new turf, concrete sidewalk, chain link fencing and gates, bleachers, irrigation system, and soccer goal posts; and

•                     Installation of new sport lighting poles, foundations, and electrical system.

 

The contract has been satisfactorily completed by Zeco, Inc. There were additional quantities of concrete sidewalk, landscaping work, and other approved change orders, in the amount of $213,677.31, bringing the final project cost to $2,358,256.31. These additional costs are within the previously approved contingency amount.

 

The following table summarizes the increase to bid items and change orders:

 

Change Order

Purpose

Amount

Bid Items

Increase in quantities of concrete sidewalk and landscaping work.

$40,102.62

1

Install new drain line and rock cistern.

$23,277.00

2

Remove additional trees conflicting with new soccer fields.

$7,355.00

3

Install additional fencing and posts.

$42,408.00

4

Dewater and additional concrete slurry for sport light foundations.

$59,734.69

5

Remove and dispose of additional soil from sport light foundations and landscaping work.

$40,800.00

TOTAL

 

$213,677.31

 

The work performed by Zeco, Inc. has been inspected and approved by the landscape architect, a third-party licensed inspector for compaction, and city staff.

 

The new soccer field ribbon-cutting date is scheduled for April 9, 2026, at 2:30 PM.

 

FISCAL IMPACT

 

The total construction cost, in the amount of $2,358,256.31, for the contract with Zeco, Inc., is budgeted in the following CIP Account Numbers:

 

•                     21500-212422 “Soccer Field Conversion Sigler Park” ARPA in the amount of $1,289,716.75.

 

•                     76502-762502 “Soccer Field Conversion Sigler Park” Park Dedication in the amount of $576,612.00.

 

•                     59502-592501 “Soccer Field Lighting” Municipal Lighting in the amount of $491,927.56.

 

LEGAL REVIEW

 

The City Attorney’s Office has reviewed as to form.

 

CONCLUSION

 

The contract has been satisfactorily completed by Zeco, Inc. It is recommended that the Mayor and the City Council accept the subject project and authorize the City Clerk to file a Notice of Completion with the County Clerk-Recorder’s Office.

 

ATTACHMENTS

 

1.                     Notice of Completion

2.                     Project Progress Photos

 

REVIEWED BY

 

Erin Backs, Finance Director

City Attorney’s Office

Christine Cordon, City Manager